Scope of Work Component Wise |
|
|
|
1 |
|
|
|
|
|
|
|
Progress during this week |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
KM |
KM |
100 % |
% |
|
|
|
% |
% |
% |
Financial Progress : | 25 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2019-04-04 09:16:09 |
Comment by JE in last visit : | Work in progress |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2018-11-16 10:08:20 |
Comment by SDO : | Work in progress |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-10-12 14:33:48 |
Comment by XEN on last visit : | Tubewell commissioned & chlorinator installed, pump chamber work balance. Agency instructed to complete balance work at the earliest. |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-03-21 12:52:32 |
Comment by SE on last visit : | Work progress is very slow which according to EE is due to rocky strata. |
Observation Raised by SE : | Need Intervention from Local Level |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | Kindly commission this tw immediately
|
Observation Raised by EIC : | Need urgent intervention from Local Level |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |