Progress Report

Column Filters

Weekly Reports

Name of WorkProvindg laying water supply (Barnala)
Agency NameSh. Tarsem Chand Garg
Project CostRs 179 Lacs
Start Date 10-02-2013
End Date31-03-2017
Revised Date31-03-2017
Je InchargeSh. V.K. Singh
SDE InchargeSh. Rajinder Kumar Garg
Engineer InchargeSh. Amandeep Singh
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 13.94 700
Progress during this week 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date 16.32 KM KM KM % 0 % 614 614 0 % 0 % 0 %
Financial Progress :177 Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-03-22 17:35:24
Comment by JE in last visit :Work completed
Observation Raised by JE :All is well
Date of Visit by SDO :2018-04-10 12:02:22
Comment by SDO :
Observation Raised by SDO :
Date of Visit by XEN :2018-03-18 16:34:40
Comment by XEN on last visit :Forestcaselyinsect31for principle apporoval after apporoval case for apporovalfromNGTbe taken
Observation Raised by XEN :
Date of Visit by SE :
Comment by SE on last visit :
Observation Raised by SE :
Date of Visit by CE :
Comment by CE on last visit :
Observation Raised by CE :
Comment by EIC :
Observation Raised by EIC :
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No