Scope of Work Component Wise |
|
|
2.93 |
|
|
1.76 |
200 |
400 |
|
|
|
Progress during this week |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
1.76 KM |
KM |
3.1 KM |
% |
% |
|
199 |
336 |
% |
% |
% |
Financial Progress : | 106 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-04-25 18:50:05 |
Comment by JE in last visit : | Work cOmpleted |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2018-04-06 15:00:08 |
Comment by SDO : | work completed |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-04-16 16:47:10 |
Comment by XEN on last visit : | |
Observation Raised by XEN : | |
Date of Visit by SE : | |
Comment by SE on last visit : | |
Observation Raised by SE : | |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | work not visited by Xen and above after 20 March. Others who have visited had not recorded any comments |
Observation Raised by EIC : | |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |