Progress Report

Column Filters

Weekly Reports

Name of WorkConst. of STP(Morinda)
Agency NameM/s Anand Associates, Chandigarh
Project CostRs 640 Lacs
Start Date 25-11-2016
End Date30-08-2018
Revised Date30-04-2019
Je InchargeSh. Pardeep Kumar
SDE InchargeSh. Tarun Gupta
Engineer InchargeSh. Rahul Kaushal
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 5.5
Progress during this week 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM KM KM % 100 % % % %
Financial Progress :544 Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2019-05-31 10:54:53
Comment by JE in last visit :Plant commissioned
Observation Raised by JE :All is well
Date of Visit by SDO :2019-07-02 12:40:40
Comment by SDO :STP Morinda in working order
Observation Raised by SDO :
Date of Visit by XEN :2019-08-27 15:20:59
Comment by XEN on last visit :STP in operation.
Observation Raised by XEN :
Date of Visit by SE :2019-09-27 11:16:44
Comment by SE on last visit :STP under stabilisation. Test results for sample taken by PPCB on 8/8/19 are awaited. No proper flow at outlet.. Decanters not working properly. Agency/EE to look into & sort out the issue reg RCC main.
Observation Raised by SE :
Date of Visit by CE :2018-07-12 13:12:22
Comment by CE on last visit :Civil work completed except boundary wall, road work & staff quarter. Mechanical fitting work in progress. Agency ensured that STP will be made operational by 15.09.2018.
Observation Raised by CE :
Comment by EIC :1 No visit by the officer above SDE is on record after 21st March 2. Kindly upload photos of close view of the work For Kind attn. of SE
Observation Raised by EIC :
Pending material Inspection Reports :Yes (9)-2018-04-30 01:46:22
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No