Scope of Work Component Wise |
|
0.37 |
4.6 |
|
|
|
|
1223 |
|
|
|
Progress during this week |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
0.38 KM |
3.61 KM |
% |
% |
|
|
540 |
% |
% |
% |
Financial Progress : | 221 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-12-20 14:39:59 |
Comment by JE in last visit : | work in progress |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2019-01-30 16:52:41 |
Comment by SDO : | Paver block road |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2019-03-11 12:19:27 |
Comment by XEN on last visit : | Work completed. |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-04-25 09:46:42 |
Comment by SE on last visit : | EE to coordinate with MC for earth filling in low lying areas & get balance sewer lines laid. EE asked to upload scope & progress of roadworks roadworks also & ensure its early completion. |
Observation Raised by SE : | |
Date of Visit by CE : | 2018-04-18 11:46:31 |
Comment by CE on last visit : | Sewer work 95%complete and reconditioning with dismantled tiles in progress |
Observation Raised by CE : | |
Comment by EIC : | |
Observation Raised by EIC : | |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |