Progress Report

Column Filters

Weekly Reports

Name of Workprovinding laying sewerage work(Nabha)
Agency NameSh. Kuldip Singh Contractor, Chandigarh
Project CostRs 367 Lacs
Start Date 03-10-2016
End Date28-02-2018
Revised Date28-02-2018
Je InchargeSh. Amrinder Singh
SDE InchargeSh. Sanjay Jindal
Engineer InchargeMs Lata Chauhan
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 0.5 10.73 1600
Progress during this week 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM .77 KM 5.89 KM % % 615 % % %
Financial Progress :313 Lacs
Physical Progress :85 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-06-19 10:24:04
Comment by JE in last visit :Work Completed
Observation Raised by JE :All is well
Date of Visit by SDO :2018-06-19 10:30:38
Comment by SDO :Work completed.
Observation Raised by SDO :
Date of Visit by XEN :2018-06-22 11:37:18
Comment by XEN on last visit :Work completed
Observation Raised by XEN :
Date of Visit by SE :
Comment by SE on last visit :
Observation Raised by SE :
Date of Visit by CE :2018-03-22 14:25:51
Comment by CE on last visit :As desired by Hon'bLe Minister forest punjab route for main sewer being finalised along existing disposal works Choudhary mjara village road nabha
Observation Raised by CE :
Comment by EIC :
Observation Raised by EIC :Need urgent intervention from Local Level
Pending material Inspection Reports :Yes (1)-2018-05-07 21:54:12
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No