Scope of Work Component Wise |
|
|
8.31 |
|
|
7.89 |
300 |
300 |
|
|
|
Progress during this week |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
300 KM |
0 KM |
8.31 KM |
0 % |
0 % |
|
300 |
300 |
0 % |
0 % |
0 % |
Financial Progress : | 480 Lacs |
Physical Progress : | 99 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-04-17 09:41:55 |
Comment by JE in last visit : | All works completed ,in some places the soil has to be raised ,it has asked the agency to do it. |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | |
Comment by SDO : | |
Observation Raised by SDO : | |
Date of Visit by XEN : | |
Comment by XEN on last visit : | |
Observation Raised by XEN : | |
Date of Visit by SE : | |
Comment by SE on last visit : | |
Observation Raised by SE : | |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | No visit in last 15 days by officer above JE is on record |
Observation Raised by EIC : | Need urgent intervention from Local Level |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |