Urban Environment Improvement Project-II Constituency wise Data Back to Summary

Column Filters

Name of District Name of Constituency Name of MC/NP Allocation (₹ in Lacs) No of Works Approved (DUIC) Amount approved by DUIC (₹ in Lacs) No of Works (After vetting at Headquarter Level) Vetted Amount (₹ in Lacs) Funds released by PIDB (₹ in Lacs) No of Works (Work Tendered) Estimated Amount (Work Tendered) (₹ in Lacs) No of Works (Work Alloted) Alloted Amount (Work Alloted) (₹ in Lacs) No of Works (Work Started) Alloted Amount (Work Started) (₹ in Lacs) No of Works (Work Completed) Alloted Amount (Work Completed) (₹ in Lacs) Amount of UC submitted to PIDB (Funds utilised) (₹ in Lacs) Pending amount yet to be released by PIDB from allocation (₹ in Lacs) Work Started in % Work Completed in %
FAZILKA Abohar MC AboharView Detail 3611 37 1506 37 1494.71 1181.224 37 1494.71 35 1346.39 35 1346.39 0 0 0 95% 0%
FAZILKA Fazilka FazilkaView Detail 800 0 0 0 0 640 0 0 0 0 0 0 0 0 0 0% 0%
FAZILKA Jalabad JalabadView Detail 900 38 900 27 609.32 487.456 25 347.61 25 347.61 23 262.77 0 0 0 85% 0%
FAZILKA Jalabad ArniwalaView Detail 100 10 102.41 10 100 80 10 100 10 100 10 100 0 0 0 100% 0%