Urban Environment Improvement Project-II Constituency wise Data Back to Summary

Column Filters

Name of District Name of Constituency Name of MC/NP Allocation (₹ in Lacs) No of Works Approved (DUIC) Amount approved by DUIC (₹ in Lacs) No of Works (After vetting at Headquarter Level) Vetted Amount (₹ in Lacs) Funds released by PIDB (₹ in Lacs) No of Works (Work Tendered) Estimated Amount (Work Tendered) (₹ in Lacs) No of Works (Work Alloted) Alloted Amount (Work Alloted) (₹ in Lacs) No of Works (Work Started) Alloted Amount (Work Started) (₹ in Lacs) No of Works (Work Completed) Alloted Amount (Work Completed) (₹ in Lacs) Amount of UC submitted to PIDB (Funds utilised) (₹ in Lacs) Pending amount yet to be released by PIDB from allocation (₹ in Lacs) Work Started in % Work Completed in %
FATEHGARH SAHIB Bassi Pathana KhamanoView Detail 120 21 141.7 18 120 96 18 120 18 116.41 17 108.16 5 31.58 0 94% 28%
FATEHGARH SAHIB Bassi Pathana Bassi PathanaView Detail 180 12 218.11 12 180 144 12 217.37 12 190.41 10 177.63 0 0 0 83% 0%
FATEHGARH SAHIB Amloh AmlohView Detail 290 25 369.4 24 290 232 24 290 20 242.41 20 242.41 2 22.1 0 83% 8%
FATEHGARH SAHIB Amloh GobindgarhView Detail 710 1 959 1 1152.3 387.44 0 0 0 0 0 0 0 0 0 0% 0%
FATEHGARH SAHIB Fathegarh Sahib SirhindView Detail 500 33 500 31 476.67 381.34 28 348.85 27 310.15 27 310.15 1 1.95 0 87% 3%