Name of District Name of Constituency Name of MC/NP Allocation (₹ in Lacs) No of Works Approved (DUIC) Amount approved by DUIC (₹ in Lacs) No of Works (After vetting at Headquarter Level) Vetted Amount (₹ in Lacs) Funds released by PIDB (₹ in Lacs) No of Works (Work Tendered) Estimated Amount (Work Tendered) (₹ in Lacs) No of Works (Work Alloted) Alloted Amount (Work Alloted) (₹ in Lacs) No of Works (Work Started) Alloted Amount (Work Started) (₹ in Lacs) No of Works (Work Completed) Alloted Amount (Work Completed) (₹ in Lacs) Amount of UC submitted to PIDB (Funds utilised) (₹ in Lacs) Pending amount yet to be released by PIDB from allocation (₹ in Lacs) Work Started in % Work Completed in %
MUKTSAR Muktsar BariwalaView Detail 120 6 127.44 6 120 96 6 120 9 98.22 6 98.22 2 22 0 100% 33%
MUKTSAR Muktsar Sri Muktsar SahibView Detail 180 2 185.02 2 180 144 2 180 2 167.11 2 167.11 0 0 0 100% 0%
MUKTSAR Malout MaloutView Detail 200 11 206.43 11 200 160 11 200 10 165.56 9 131.56 5 64.06 0 82% 45%
MUKTSAR Giderbaha GiderbahaView Detail 500 48 535.33 31 382.95 400 31 382.95 30 317.15 26 299.8 2 125.02 0 84% 6%