AAYUSH ARUNAM - 3rd Party |
Jalandhar 1 |
provinding laying sewerage work (under NRCP ) |
Need urgent intervention from Local Level |
Report no -EIL/PMIDC/JLN/JLN CITY/PWSSB/AGG.NO 34 OF 2016-17/02 DATED 19.04.2018
progress at the time of audit-95%(as per Pwssb officer) |
|
NO |
18-05-10 |
Wapcos - 3rd Party |
Patiala 1 |
provinding laying sewerage work |
All is well |
Progress is comparable with the last visit by third party on 13.07.2017 |
|
NO |
18-04-04 |
AAYUSH ARUNAM - 3rd Party |
Hoshiarpur |
Providing sewerage work & const. of MPS |
Need urgent intervention from Local Level |
Report no-EIL/PMIDC/HSP/PWSSB/27/02
Comments for compliance are furnished as under:-
1.Test report of construction material to be submitted
2.MTC for cement and steel to be submitted
3.Challan for construction material to be submitted.
4.Time extensi |
|
NO |
18-05-03 |
AAYUSH ARUNAM - 3rd Party |
Hoshiarpur |
Const. of OHSR |
Need urgent intervention from Local Level |
Report no -EIL/PMIDC/HSP/PWSSB/38 OF 2016-17/04
progress at the time of visit-90%(as per PWSSB officer) |
|
NO |
18-05-05 |
AAYUSH ARUNAM - 3rd Party |
Hoshiarpur |
Boring & installation of Tubewell |
Need urgent intervention from Local Level |
Report no - EIL/PMIDC/HSP/PWSSB/SE9118 OF 18-11-16/01
Progress at the time of visit -35% (as per Pwssb officer) (progress is on work order wise not as per location wise) |
|
NO |
18-05-05 |
AAYUSH ARUNAM - 3rd Party |
Hoshiarpur |
Providing water supply |
Need urgent intervention from Local Level |
Report no -EIL/PMIDC/HSP/PWSSB/2667-69/03
Progress at the time of visit -100%(of hariyana town)(progress as per Pwssb officer) |
|
NO |
18-05-05 |
AAYUSH ARUNAM - 3rd Party |
Hoshiarpur |
Provindg laying water supply |
Need urgent intervention from Local Level |
Report no -EIL/PMIDC/HSP/PWSSB/2667-69/2
Work order Progress at the time of visit 60% (of mahilpur)(progress as per Pwssb officer) |
|
NO |
18-05-05 |
AAYUSH ARUNAM - 3rd Party |
Hoshiarpur |
Providing water supply & sewerage work |
Need urgent intervention from Local Level |
Report no -EIL/PMIDC/HSP/PWSSB//1642/02
Progress at the time of site visit -30%(as per Pwssb officer) |
|
NO |
18-05-05 |
AAYUSH ARUNAM - 3rd Party |
Hoshiarpur |
Boring & installation of Tubewell |
Need urgent intervention from Local Level |
Report no-EIL/PMIDC/HSP/PWSSB/39 OF 2016-17/01
progress at the time of visit -35%(as per Pwssb officer) |
|
NO |
18-05-05 |
AAYUSH ARUNAM - 3rd Party |
Hoshiarpur |
Providing sewerage work & const. of MPS |
Need urgent intervention from Local Level |
Report no -EIL/PMIDC/HSP/PWSSB/29/01
Progress at the time of visit-10%(as per Pwssb officer) |
|
NO |
18-05-05 |
AAYUSH ARUNAM - 3rd Party |
Hoshiarpur |
Providing and laying intercepting sewer link along with bhangichoe |
Need urgent intervention from Local Level |
Report no -EIL/PMIDC/HSP/PWSSB/30/01
Progress at the time of visit - yet to start (intial visit)
(progress as per Pwssb officer) |
|
NO |
18-05-05 |
GULSHAN KUMAR - 3rd Party |
Hoshiarpur |
sewerage work & const. of MPS |
Need urgent intervention from Local Level |
Report no EIL/PMIDC/WSSB/BALACHOR/16/02
Progress time of visit -30% (As per pwssb officer) |
|
NO |
18-05-05 |
GULSHAN KUMAR - 3rd Party |
Hoshiarpur |
Providing Sewerage works (Under Urban Mission) |
Need urgent intervention from Local Level |
Report No EIL/PMIDC/WSSB/NSR/NSR/7317/02
Progress as per time of visit-20% (As per pwssb officers)
|
|
NO |
18-05-05 |
GULSHAN KUMAR - 3rd Party |
Hoshiarpur |
Providing Sewerage work (under NRCP) |
Need urgent intervention from Local Level |
Report No EIL/PMIDC/WSSB/NSR/NSR-BANGA/02/02
Progress as per time of visit-85% (As per pwssb officers)
Above work order amount -253.62
|
|
NO |
18-05-05 |
GULSHAN KUMAR - 3rd Party |
Hoshiarpur |
Providing water supply (under PMIDC) |
Need urgent intervention from Local Level |
Report No EIL/PMIDC/WSSB/NSR/NSR-BANGA/01/01
Allotment no 01 (2016-17)
Amount given DNIT or contract document -105.35
Progress as per time of visit-45% (As per pwssb officers)
|
|
NO |
18-05-05 |
OM PRAKASH MAHAWAR - 3rd Party |
Gurdaspur |
Prov.and laying S.W pipe sewer in Kothe Behrampur area |
Need urgent intervention from Local Level |
Report no-EIL/PMIDC/PWSSB/GUR/GUR/2263/03
Prog6at the time of visit- 100%(as per pwssb officer) |
|
NO |
18-05-17 |
NIKHIL SAINI - 3rd Party |
Jalandhar 2 |
Prov W/S and Sewerage in extended limit area Phagwara |
Need urgent intervention from Local Level |
REPORT NO EIL/PMIDC/PWR/PWR(PWSSB)/02-EE LETTER NO 1391/04
Progress on the date of visit-19-07-17 (As per pwssb officers) |
|
NO |
18-05-17 |
NIKHIL SAINI - 3rd Party |
Jalandhar 2 |
Providng 100% W/S old limit phagwara |
Need urgent intervention from Local Level |
REPORT NO EIL/PMIDC/PWR/PWR/02-EE LETTER NO 2965/03
Progress on the date of visit-20-07-17 (As per pwssb officers) |
|
NO |
18-05-17 |
GULSHAN KUMAR - 3rd Party |
Hoshiarpur |
Const. of OHSR |
Need urgent intervention from Local Level |
EPORT NO EIL/PMIDC/WSSB)/NSR/BANGA/38/01
Progress on the date of visit-10 % dated 15-05-17 (As per pwssb officers) |
|
NO |
18-05-18 |
GULSHAN KUMAR - 3rd Party |
Moga |
Provindg laying Sewerage work |
Need urgent intervention from Local Level |
REPORT NO EIL/PMIDC/PWSSB/MOGA/DK/2328/03
Progress on the date of visit-100 % Dated 03-04-17 (As per pwssb officers) |
|
NO |
18-05-18 |
NIKHIL SAINI - 3rd Party |
Jalandhar 2 |
Providing water supply ,OHSR, installation of Tubewell & sewerage work |
Need urgent intervention from Local Level |
REPORT-NO-EIL/PMIDC/PWR/PWR/02-EE LETTER NO-884/03
PROGRESS AT TIME OF VISIT 80%(AS PER PWSSB OFFICER) |
|
NO |
18-05-18 |
NIKHIL SAINI - 3rd Party |
Jalandhar 2 |
provinding laying sewerage work & const. of MPS & STP |
Need urgent intervention from Local Level |
REPORT-NO-EIL/PMIDC/JLN/GORAYA/PWSSB/02-EE LETTER NO-4315/01
PROGRESS AT TIME OF VISIT 55%(AS PER PWSSB OFFICER) |
|
NO |
18-05-18 |
NIKHIL SAINI - 3rd Party |
Jalandhar 2 |
provinding laying sewerage work & const. of MPS & STP |
Need urgent intervention from Local Level |
REPORT-NO-EIL/PMIDC/JLN/GORAYA/PWSSB/02-EE LETTER NO-4315/01
PROGRESS AT TIME OF VISIT 55%(AS PER PWSSB OFFICER) |
|
NO |
18-05-18 |
NIKHIL SAINI - 3rd Party |
Jalandhar 2 |
Providing water supply ,OHSR, installation of Tubewell & sewerage work |
Need urgent intervention from Local Level |
REPORT-NO-EIL/PMIDC/PWR/PWR/02-EE LETTER NO-4404/03
PROGRESS AT TIME OF VISIT 60%(AS PER PWSSB OFFICER) |
|
NO |
18-05-18 |
GULSHAN KUMAR - 3rd Party |
Moga |
Provindg laying Sewerage work const. of MPS |
Need urgent intervention from Local Level |
Report No. EIL/PMIDC/PWSSB/MOGA/BK/3581/02 DATED-18.08.2017
PROGRESS AT THE TIME OF VISIT-30% AS PER PWSSB OFFICER |
|
NO |
18-07-13 |
GULSHAN KUMAR - 3rd Party |
Moga |
Providing laying water supply |
Need urgent intervention from Local Level |
Report No. EIL/PMIDC/PWSSB/MOGA/KIK/3018/03 DATED-22.08.2017
PROGRESS AT THE TIME OF VISIT-70% AS PER PWSSB OFFICER |
|
NO |
18-07-13 |
GULSHAN KUMAR - 3rd Party |
Hoshiarpur |
Providing water supply |
Need urgent intervention from Local Level |
EIL PMIDC WSSB NSR BALACHOR 25 02
PROGRESS OF WORK 70% at the time of visit and work not in progress at that time. Dated 24.07.2018 |
|
NO |
18-07-24 |
GULSHAN KUMAR - 3rd Party |
Hoshiarpur |
installing of Tubewell |
Need urgent intervention from Local Level |
EIL PMIDC WSSB NSR BALACHOR SE-8251/01
PROGRESS OF WORK AT THE TIME OF VISIT 70% as per pwssb officer and work not in progress at that time Dated 24.07.2018 |
|
NO |
18-07-24 |
DAI TUNU - 3rd Party |
Moga |
Cluster of Faridkot, Jaitu & Kotkapura |
Need Intervention from Local Level |
Before start Brick Masonary Make Brick Wet, Take care of minimum gap of Bounding of Cement Mortar, Use Plumb Bob while Masonry |
|
NO |
18-07-26 |
DAI TUNU - 3rd Party |
Moga |
Cluster of Faridkot, Jaitu & Kotkapura |
Need Intervention from Local Level |
Before start Brick Masonary Make Brick Wet, Take care of minimum gap of Bounding of Cement Mortar, Use Plumb Bob while Masonry |
|
NO |
18-07-26 |
DAI TUNU - 3rd Party |
Moga |
Cluster of Faridkot, Jaitu & Kotkapura |
Need Intervention from Local Level |
Proper Curring should be maintain and take while using of spacing bar and over lapping of bars |
|
YES |
18-07-30 |
DAI TUNU - 3rd Party |
Moga |
Cluster of Faridkot, Jaitu & Kotkapura |
Need Intervention from Local Level |
Proper slump should be check before insert the cc |
|
YES |
18-07-30 |
DAI TUNU - 3rd Party |
Moga |
Cluster of Faridkot, Jaitu & Kotkapura |
Need Intervention from Local Level |
Side locking of Paver Block with Cement Concert should be care of width of cc, Proper care while mix of Cement Concret (1:8:16) for Base (ADARESH NAGAR FDK ) |
|
YES |
18-08-02 |
DAI TUNU - 3rd Party |
Moga |
Cluster of Faridkot, Jaitu & Kotkapura |
Need Intervention from Local Level |
Side locking of Paver Block with Cement Concert should be care of width of cc, Proper care while mix of Cement Concret (1:8:16) for Base (ADARESH NAGAR FDK ) |
|
YES |
18-08-02 |
GULSHAN KUMAR - 3rd Party |
Hoshiarpur |
Providing Sewerage works (Under Urban Mission) |
Need Intervention from Local Level |
Report No EIL/PMIDC/WSSB/NSR/NSR/7317/03 dated -24.07.2018
%age of work as per PWSSB officer 30% at the time of visit |
|
NO |
18-08-24 |
GULSHAN KUMAR - 3rd Party |
Hoshiarpur |
Const. of OHSR |
Need Intervention from Local Level |
Report No EIL/PMIDC/WSSB/NSR/BANGA/38/02
dated -25.07.2018
%age of work as per PWSSB officer 75% at the time of visit |
|
NO |
18-08-24 |
AAYUSH ARUNAM - 3rd Party |
Jalandhar 2 |
Providing water supply & installation of Tubewell & sewerage work |
Need urgent intervention from Local Level |
Report no EIL/PMIDC/kpt/kpt/PWSSB/7784/01 |
|
NO |
18-08-25 |
NIKHIL SAINI - 3rd Party |
Jalandhar 1 |
Const. of MPS & Rising Main |
Need urgent intervention from Local Level |
Report no:-EIL/PMIDC/JLN/NAKODAR/01-EE/01 DATED 31-05-2017 |
|
NO |
18-08-27 |
NIKHIL SAINI - 3rd Party |
Jalandhar 1 |
Provindg laying water supply works |
Need urgent intervention from Local Level |
Report No EIL/PMIDC/PWR/PWR/02-EELETTER NO 5604/01 DATED 01-06-2017
PROGRESS OF WORK AT THE TIME OF VISIT IS 0% AS PER PWSSB OFFICER |
|
NO |
18-08-27 |
NIKHIL SAINI - 3rd Party |
Jalandhar 1 |
const. of STP |
Need urgent intervention from Local Level |
Report No EIL/PMIDC/JLN/SHAHKOT/01 WE AGG.NO 11/16-17 DATED 31-05-2017
PROGRESS OF WORK AT THE TIME OF VISIT IS 60% AS PER PWSSB OFFICER |
|
NO |
18-08-27 |
NIKHIL SAINI - 3rd Party |
Jalandhar 1 |
provinding laying sewerage work |
Need urgent intervention from Local Level |
Report No EIL/PMIDC/JLN/SHAHKOT/01-EE/PWSSB/01 DATED 31-05-2017
PROGRESS OF WORK AT THE TIME OF VISIT IS 50% AS PER PWSSB OFFICER |
|
NO |
18-08-27 |
NIKHIL SAINI - 3rd Party |
Jalandhar 1 |
Provindg laying water supply works |
Need urgent intervention from Local Level |
Report No EIL/PMIDC/PWR/PWR/02-EELETTER NO 5604/01 DATED 01-06-2017
PROGRESS OF WORK AT THE TIME OF VISIT IS 0% AS PER PWSSB OFFICER |
|
NO |
18-08-27 |
NIKHIL SAINI - 3rd Party |
Jalandhar 2 |
provinding laying sewerage work & const. of MPS & STP |
Need urgent intervention from Local Level |
Report No EIL/PMIDC/JLN/GORAYA/02-EELETTER NO 4315/01 DATED 27-02-2017
PROGRESS OF WORK AT THE TIME OF VISIT IS 55% AS PER PWSSB OFFICER |
|
NO |
18-08-27 |
NIKHIL SAINI - 3rd Party |
Jalandhar 2 |
Prov. STP at Phillaur |
Need urgent intervention from Local Level |
Report No EIL/PMIDC/JLN/PHR/02-EELETTER NO 2787/01 DATED 27-02-2017
PROGRESS OF WORK AT THE TIME OF VISIT IS 35% AS PER PWSSB OFFICER |
|
NO |
18-08-27 |
NIKHIL SAINI - 3rd Party |
Jalandhar 1 |
Const. of MPS & Rising Main |
Need urgent intervention from Local Level |
Report No EIL/PMIDC/JLN/NAKODAR/01-EELETTER NO - DATED 31-05-2017
PROGRESS OF WORK AT THE TIME OF VISIT IS 60% AS PER PWSSB OFFICER |
|
NO |
18-08-27 |
AAYUSH ARUNAM - 3rd Party |
Jalandhar 1 |
Const. of MPS |
Need urgent intervention from Local Level |
Report no-EIL/PMIDC/JLN/ADAMPUR/PWSSB/AGG. NO.52OF 2016-17/01
PROGRESS 65% |
|
NO |
18-08-28 |
DAI TUNU - 3rd Party |
Moga |
Cluster of Faridkot, Jaitu & Kotkapura |
Need urgent intervention from Local Level |
General equipment should be kept at site for checking the quality of the works |
|
YES |
18-08-31 |
DAI TUNU - 3rd Party |
Ferozpur |
Providing laying water supply & construction of OHSR and WTP |
Need Intervention from Local Level |
Expansion joints should fill immidetlly, Base Panel of WTP C.C 1:3:6 should be even depth, Wet the Bricks before start the daily works, Regular test of Slump Test |
|
YES |
18-09-13 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing sewerage work |
All is well |
Re constructed of MH due to not as per design and drawing |
|
NO |
18-09-16 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing sewerage work |
All is well |
Re constructed of MH due to not as per design and drawing |
|
NO |
18-09-16 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing Laying Water Supply & const. of WTP |
All is well |
CWT Steel shuttering and steel work under progress |
|
NO |
18-09-16 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing Laying Water Supply & const. of WTP |
All is well |
Ramp cutting for 800 mm pipe laying at Fazilka road |
|
NO |
18-09-19 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing Laying Water Supply & const. of WTP |
All is well |
Pump chamber pcc and raft steel laying work under progress |
|
NO |
18-09-22 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing sewerage work |
All is well |
Work stop due to heavy rain dewatering work under progress |
|
NO |
18-09-25 |
Arun Kumar Sharma - 3rd Party |
Amritsar 2 |
Providing laying water supply |
All is well |
Pump chamber reinforced laying under progress |
|
YES |
18-09-26 |
Arun Kumar Sharma - 3rd Party |
Amritsar 2 |
Providing laying water supply |
All is well |
Pump chamber bottom slab pcc M15 28 days cube testing in lab. |
|
YES |
18-09-26 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing sewerage work |
All is well |
Construction of MH work under progress at Malot Road on 800 mm line |
|
NO |
18-09-27 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing sewerage work |
Need Intervention from Local Level |
This MH slab has been casting since three days but curring is not properly at gali No. 10 Panchpir tiba |
|
YES |
18-09-27 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing sewerage work |
All is well |
800 mm dia sewer line laying at new Fazilka but back side earth soil has been not compacted properly. |
|
YES |
18-09-27 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing Laying Water Supply & const. of WTP |
All is well |
Work under progress of CWT Slab casting grade M25 at new WTP site |
|
NO |
18-09-28 |
Manish Kumar Awasthi - 3rd Party |
Ludhiana |
Const. of STP (Under AMRUT) |
All is well |
Layout plan photo attached. DTL, ACM and AE of PDMC are also at site. |
|
NO |
18-10-02 |
Hakam Chand Sharma - 3rd Party |
Ludhiana |
Const. of STP (Under AMRUT) |
All is well |
Preparation for visit of worthy secretary local government PB layout plan D T L ,A E PRESENT |
|
NO |
18-10-02 |
Manish Kumar Awasthi - 3rd Party |
Ludhiana |
Const. of STP (Under AMRUT) |
All is well |
Layout plan of STP attached. unitwise presentation to PS sir will be told on this plan. DTL, ACM and AE, PDMC are at site for visit of P. S. sir. |
|
NO |
18-10-02 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing Laying Water Supply & const. of WTP |
All is well |
Earth work excavation work under progress of WTP foundation. |
|
NO |
18-10-09 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing sewerage work |
All is well |
Brick sample taken at Ajimgarr for lab test |
|
NO |
18-10-09 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing sewerage work |
All is well |
400 mm dia sewer line trunches filled work in progress but soil compation has not been layer by layer |
|
NO |
18-10-17 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing Laying Water Supply & const. of WTP |
All is well |
Pump chamber wall concert M30and inner chaja Slab shuttering work in progress |
|
NO |
18-11-05 |
GULSHAN KUMAR - 3rd Party |
Hoshiarpur |
Providing Sewerage works (Under Urban Mission) |
Need urgent intervention from Local Level |
EIL/PMIDC/WSSB/NSR/NSR/7317/04. DATED 14.09.2018. PROGEESS OF WORK AS PER PWSSB OFFICER 50% |
|
NO |
18-11-12 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing Laying Water Supply & const. of WTP |
Need Intervention from Local Level |
Old Fazilka road, Construction of MH brick mortar vertical joint being not specifications 1) Dry brick in used 2)cement mortar ratio not properly used in MH brick work |
|
NO |
18-11-14 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing sewerage work |
All is well |
Construction of MH work in progress at Dharamnagri |
|
NO |
18-12-06 |
Wapcos - 3rd Party |
Ropar |
Const. of STP |
All is well |
STP work is in progress |
|
NO |
19-04-11 |
Wapcos - 3rd Party |
Sangrur |
Cluster of Sangrur & Dhuri |
All is well |
Stp work just started and MPS work in progress .
Overall work is less than 10% (Sangrur) 4MLD
Sewerage networKing 80% completed. |
|
YES |
19-05-13 |
Wapcos - 3rd Party |
Sangrur |
Cluster of Sangrur & Dhuri |
All is well |
Stp work just started and MPS work in progress .
Overall work is less than 10% (Sangrur) 4MLD
Sewerage networKing 80% completed. |
|
YES |
19-05-13 |
Wapcos - 3rd Party |
Sangrur |
Cluster of Sangrur & Dhuri |
All is well |
Stp 4 MLD progress is less than 10%
Sewerage networking progress is 80% |
|
YES |
19-05-13 |
Wapcos - 3rd Party |
Sangrur |
Cluster of Sangrur & Dhuri |
All is well |
Stp 4 MLD progress is less than 10%
Sewerage networking progress is 80% |
|
YES |
19-05-13 |
Wapcos - 3rd Party |
Sangrur |
Cluster of Sangrur & Dhuri |
All is well |
STP work just started.
Sw pipe sewer work in progress at moti nagar
Work for interlocking tile in progress |
|
YES |
19-05-13 |
Wapcos - 3rd Party |
Sangrur |
Cluster of Sangrur & Dhuri |
All is well |
5 MLD STP work just started and progress is less than 10% (Dhuri)
Interlocking tile work in sangatpura is in progress.
200 mm sewer work in progress. |
|
NO |
19-05-17 |
Wapcos - 3rd Party |
Mansa |
Cluster Barretta, Bhikhi, Mansa , Boha , Sardulgarh, Budhalada |
All is well |
During visit interlocking tile work was in progress
Sewer line progress = 3.65 km
|
|
NO |
19-06-17 |
Wapcos - 3rd Party |
Mansa |
Cluster Barretta, Bhikhi, Mansa , Boha , Sardulgarh, Budhalada |
Need Intervention from Local Level |
During visit laying sewer 400mm i/d was in progress
STP progress 2%
STP boundary wall work in progress |
|
NO |
19-06-17 |
Wapcos - 3rd Party |
Mansa |
Cluster Barretta, Bhikhi, Mansa , Boha , Sardulgarh, Budhalada |
All is well |
WTP work is in progress (1%)
OHSR progress 90% |
|
NO |
19-06-17 |
Wapcos - 3rd Party |
Mansa |
Cluster Barretta, Bhikhi, Mansa , Boha , Sardulgarh, Budhalada |
All is well |
During visit interlocking tile work was in progress
OHSR 100% complete |
|
NO |
19-06-17 |
Wapcos - 3rd Party |
Patiala 2 |
Cluster of Bassi Pathana & Sirhind |
All is well |
STP work progress is under 20%.
MPS work progress is about 60-70%
Lateral sewer 8" work is in progress |
|
NO |
19-07-26 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing Laying Water Supply & const. of WTP |
All is well |
20 mm & 10 mm aggregate has been recived and checked at site and lab.found résult within limits |
|
NO |
19-10-07 |
Arun Kumar Sharma - 3rd Party |
Abohar |
Providing Laying Water Supply & const. of WTP |
All is well |
10 mm & 20 mm aggregate has been checked at site found observation is OK. |
|
NO |
19-10-07 |