Scope of Work Component Wise |
|
4.729 |
10.666 |
|
|
|
|
3000 |
1 |
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
4.79 KM |
9.0 KM |
% |
% |
|
|
2500 |
100 % |
% |
% |
Financial Progress : | Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2019-07-19 11:22:15 |
Comment by JE in last visit : | Work stopped due to heavy rain |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2019-07-19 11:23:35 |
Comment by SDO : | Work stopped due to rain |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2019-09-12 17:20:37 |
Comment by XEN on last visit : | concreting work is in progress |
Observation Raised by XEN : | |
Date of Visit by SE : | |
Comment by SE on last visit : | |
Observation Raised by SE : | |
Date of Visit by CE : | 2018-03-24 09:57:52 |
Comment by CE on last visit : | The colour board errected at site of STP is not as per Pwssb instructions.EE advised to change it.
E E in form that the rising main taken In DPR only
50 mt which is not proper disposal of treated waste Water.The water will be used for irrigation
and surplus water to dispose at proper place,
EE advised to prepare proper proposal for disposal of surplus waste Water |
Observation Raised by CE : | |
Comment by EIC : | |
Observation Raised by EIC : | |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |