Progress Report

Column Filters

Weekly Reports

Name of WorkProvindg laying water supply (Gardhiwala)
Agency NameNation Builders, Pathankot
Project CostRs 38 Lacs
Start Date 12-05-2016
End Date11-11-2016
Revised Date11-11-2016
Je InchargeDeepak Palial
SDE InchargeSh. Daljit Kumar Bhandari
Engineer InchargeSh. Ashish Rai
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 2.65 346
Progress during this week (Week 4) 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM KM KM % % 149 % % %
Financial Progress : Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-05-07 10:18:16
Comment by JE in last visit :work completed and final bill has been passed from audit.
Observation Raised by JE :All is well
Date of Visit by SDO :2018-05-07 10:47:31
Comment by SDO :Bill of agency finalized and passed from audit
Observation Raised by SDO :
Date of Visit by XEN :2018-05-08 10:41:51
Comment by XEN on last visit :Work completed ,final bill passed and checked from audit too.
Observation Raised by XEN :
Date of Visit by SE :
Comment by SE on last visit :
Observation Raised by SE :
Date of Visit by CE :
Comment by CE on last visit :
Observation Raised by CE :
Comment by EIC :
Observation Raised by EIC :
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No