Progress Report

Column Filters

Weekly Reports

Name of WorkComposite work of Ferozepur, Talwandi bhai , Dharmkot, Makhu (Ferozepur)
Agency NameM/S GSJ Envo Ltd.
Project CostRs 3540 Lacs
Start Date 05-09-2013
End Date31-12-2017
Revised Date30-11-2019
Je InchargeSh. Gurwinder Singh
SDE InchargeSh. Gulshan Kumar
Engineer InchargeSh.Pritpal Singh
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 3.32 40.03 18
Progress during this week (Week 4) 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM 2.77 KM 40.06 KM % 94 % % % %
Financial Progress :3803.23 Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2019-06-15 13:03:00
Comment by JE in last visit :SBR basin 2 hydro test work is in progress
Observation Raised by JE :All is well
Date of Visit by SDO :2019-07-31 14:31:42
Comment by SDO :CCT to Drain outlet channel tile fixing work is in progress.
Observation Raised by SDO :
Date of Visit by XEN :2019-07-31 14:49:40
Comment by XEN on last visit :Effulent channel tile fixing work is in progress
Observation Raised by XEN :
Date of Visit by SE :
Comment by SE on last visit :
Observation Raised by SE :
Date of Visit by CE :2019-05-08 16:29:46
Comment by CE on last visit :The work of installation of classifier unit , mech.bar screens ,is going on in primary unit. Decanter along with machinary .has been installed. Centrifuse unit has been completed and sludge house unit has also been completed.. Hydro testing of sbr basin 1 of stp is in progress. Quality of workmanship has not been improved yet. Cct,admin block work has also been completed.. The work of road construction and internal sewerage is yet to be completed.. Xen has been directed to get the work of stp commissioned at earliest.
Observation Raised by CE :
Comment by EIC :KIND ATTENTION XEN 1. Visit of officer above SE and CE during last 30 days is not on record 2. Kindly upload work component's close view photo to see the quality and workmanship.Avoid self / equipment / machinery etc. or taken from distance photos 3.Kindly take care of dismantled material plz
Observation Raised by EIC :Need urgent intervention from Local Level
Pending material Inspection Reports :Yes (13)-2018-05-04 04:12:32
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No