Scope of Work Component Wise |
|
1.55 |
14.83 |
|
|
|
|
2097 |
|
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
1.55 KM |
15.92 KM |
% |
% |
|
|
1169 |
% |
% |
% |
Financial Progress : | 814.28 Lacs |
Physical Progress : | 100% % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-11-28 09:03:29 |
Comment by JE in last visit : | Road marking of cantt road is in progress. Agency is instructed to complete the boundary wall of mps. |
Observation Raised by JE : | Need Intervention from Local Level |
Date of Visit by SDO : | 2018-11-29 12:13:23 |
Comment by SDO : | Instructed to fill the joints of biundary wall properly before snowcem |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-11-29 12:06:31 |
Comment by XEN on last visit : | Cope of wall and joints are not properly filled.... before final of bill...it should be correct....Noted |
Observation Raised by XEN : | Need Intervention from Local Level |
Date of Visit by SE : | |
Comment by SE on last visit : | |
Observation Raised by SE : | |
Date of Visit by CE : | 2018-06-04 16:55:45 |
Comment by CE on last visit : | The laying of 200 mm sw pipe sewer is i prgress.construction of 1.5×.90 mt size man hole work going on.
94%sewer completed.
Machinary at MpS 3 no replaced.
Construcion of road work 36%completed.
In progrees now,prgress of this component is slow.
Xen is directed take action às per aggrement.for not starting cantt road, wbm work laid... |
Observation Raised by CE : | |
Comment by EIC : | Kindly upload the close viewed photos so that the quality of work can be seen
No visit by EE SE and CE is on record |
Observation Raised by EIC : | Need urgent intervention from Local Level |
Pending material Inspection Reports : | Yes (1)-2018-05-15 07:44:10 |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |