Scope of Work Component Wise |
|
|
|
|
|
7.973 |
|
|
|
1 |
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
7.17 KM |
KM |
KM |
% |
% |
|
|
|
% |
100 % |
% |
Financial Progress : | 323.58 Lacs |
Physical Progress : | 99% % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-05-18 09:12:17 |
Comment by JE in last visit : | Railway crossing pending |
Observation Raised by JE : | Red Flag |
Date of Visit by SDO : | 2018-05-18 09:16:39 |
Comment by SDO : | Railway crossing pending.payment made to Railway Deptt. |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-05-11 19:26:11 |
Comment by XEN on last visit : | Instruct to sde fazilka to contact railway department for early tendering of crossing |
Observation Raised by XEN : | |
Date of Visit by SE : | |
Comment by SE on last visit : | |
Observation Raised by SE : | |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | 1. No visit by SE/CE during last 30 days is on record
2. kindly upload close view clear photos of work showing quality contents
3.Fund problem is over now. Send your requirement with copy of passed bill |
Observation Raised by EIC : | Need urgent intervention from Local Level |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |