Progress Report

Column Filters

Weekly Reports

Name of Workprovinding laying sewerage work(Amloh)
Agency NameSh. Jai Bhushan Malik
Project CostRs 1046 Lacs
Start Date 14-10-2016
End Date13-07-2017
Revised Date30-09-2018
Je InchargeSh. Ramandeep Singh
SDE InchargeSh. Gagan Garg
Engineer InchargeSh. Sabjit Singh
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 0.88 28.79 3200
Progress during this week (Week 4) 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM .85 KM 27.99 KM % % 2280 % % %
Financial Progress :100 Lacs
Physical Progress :1036 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2019-01-01 10:05:50
Comment by JE in last visit :CC WORK 1 :2 :4 IN PROGRESS AT TAKIYA MOHALLA AMLOH
Observation Raised by JE :Red Flag
Date of Visit by SDO :2019-04-22 09:26:47
Comment by SDO :No work in progress
Observation Raised by SDO :
Date of Visit by XEN :2018-12-13 14:21:19
Comment by XEN on last visit :Dressing work in progress for laying CC 1:8:16 in Nawan Nagar.
Observation Raised by XEN :
Date of Visit by SE :
Comment by SE on last visit :
Observation Raised by SE :
Date of Visit by CE :2018-03-22 16:13:20
Comment by CE on last visit :Manhole construction in progress. Work found satisfactory
Observation Raised by CE :
Comment by EIC :No visit by any one above JE Kindly upload the close viewed photos of the work so that quality can be seen
Observation Raised by EIC :Need urgent intervention from Local Level
Pending material Inspection Reports :Yes (3)-2018-06-05 03:50:47
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No