Progress Report

Column Filters

Weekly Reports

Name of Workconstruction of OHSR(Ajnala)
Agency NameM/S Natha Singh Contractors
Project CostRs 89 Lacs
Start Date 23-12-2016
End Date23-09-2017
Revised Date23-09-2017
Je InchargeSh. Gurbhej Singh
SDE InchargeSh. Harpreet Singh
Engineer InchargeSh Pankaj Jain
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 1 (2Lac gln.)
Progress during this week (Week 4) 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM KM KM % % % 100 % %
Financial Progress : Lacs
Physical Progress : %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-07-12 17:14:27
Comment by JE in last visit :This party EIL inspection is pending
Observation Raised by JE :All is well
Date of Visit by SDO :2018-07-12 17:29:15
Comment by SDO :Third party EIL inspection is pending
Observation Raised by SDO :
Date of Visit by XEN :2018-07-12 17:35:05
Comment by XEN on last visit :Work of OHSR is completed
Observation Raised by XEN :
Date of Visit by SE :2018-03-21 15:45:04
Comment by SE on last visit :The finishing of central Piller is bad. Railing not proper nor painted.No expension joints kept on PP & inside floor. The OHSR under testing and some sepage was seen on container wall and bottom done.
Observation Raised by SE :Need urgent intervention from Local Level
Date of Visit by CE :
Comment by CE on last visit :
Observation Raised by CE :
Comment by EIC :If work is completed then prepare the final bill and remove it from the portal
Observation Raised by EIC :Need urgent intervention from Local Level
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No