Name of Work | Providing water supply & sewerage work(Goniana) |
Agency Name | Sh. Gurmeet Singh, Cont. Kotkapura |
Project Cost | Rs 83 Lacs |
Start Date | 20-04-2015 |
End Date | 19-11-2016 |
Revised Date | 19-11-2016 |
Je Incharge | Sh. Gurprem Singh |
SDE Incharge | |
Engineer Incharge | Sh. Gurvinder Pal Singh |
Components | Program water supply | Main sewer | Lateral sewer | Tubewell | Stp | Water supply | Water supply conn | Sewer conn | Mps | Ohsr | Wtp |
---|---|---|---|---|---|---|---|---|---|---|---|
Scope of Work Component Wise | 1.735 | 1.175 | 165 | 296 | |||||||
Progress during this week (Week 4) | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |