Name of WorkConstruction of OHSR, UGSR, Pump chamber, rising main, clear water sump well, distribution lines, pumping machinery etc at Pujjan Wala Mohalla at Bathinda(Bathinda)
Agency NameM/s Kulwant Singh Sandhu
Project CostRs 169 Lacs
Start Date 07-02-2019
End Date06-02-2020
Revised Date06-02-2020
Je InchargeSh. Maninder Singh
SDE InchargeSh. Vikramjit Singh
Engineer InchargeSh. Gurvinder Pal Singh
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 2.478 2
Progress during this week (Week 4) 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date 1150 KM KM KM % % % 100 % %
Financial Progress : Lacs
Physical Progress : %
Is any observation pending by 3rd Party :
Date of Visit by Je:2019-07-19 17:24:51
Comment by JE in last visit :Today visited site. Ohsr 3rd brace coloumn work concreting was in progress . Pipe work delayed due to not reaching of pipe at site. But 150 mm pipe reached at site and stack along road
Observation Raised by JE :Red Flag
Date of Visit by SDO :2019-07-19 17:32:12
Comment by SDO :Agreed with je comments .ohsr construction work is running as per target but ws laying work is slow pipes laid at
Observation Raised by SDO :
Date of Visit by XEN :2019-07-19 17:36:02
Comment by XEN on last visit :Material not stagged properly.Agency is advised to take precautionary measure as site is very combusted for OHSR.Sieve apparatus is not at site.Civil work of UGSR completed.Work above third brace is in progress.
Observation Raised by XEN :
Date of Visit by SE :
Comment by SE on last visit :
Observation Raised by SE :
Date of Visit by CE :
Comment by CE on last visit :
Observation Raised by CE :
Comment by EIC :
Observation Raised by EIC :
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No