Scope of Work Component Wise |
|
10.73 |
63.14 |
|
1 No (20) |
|
|
7200 |
1 |
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
0 KM |
10.12 KM |
63.97 KM |
0 % |
100 % |
|
|
5740 |
100 % |
0 % |
0 % |
Financial Progress : | 9085.52 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2019-07-29 13:05:08 |
Comment by JE in last visit : | Interlocking tile work in progress at bhaini basti at Barnala |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2019-07-22 12:27:43 |
Comment by SDO : | Interested locking work in progress |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2020-02-04 15:40:08 |
Comment by XEN on last visit : | Work of 1100 mm dia sewer is in progress. Agency is directed to complete balance work earliest |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-08-09 16:13:59 |
Comment by SE on last visit : | Mechanical work of STP in progress. STP & MPS likely to be completed by Dec. IL pavers work was in progress on Gali no 8, Baharli have listed, Sangrur. Cross profile/camber of road was not correct as there were local depressions. EE & Agency were asked to dismantle and relay the defective work.Agency asked to start main sewer on Bajakhana to Bus stand Road. Major length of main sewer held up on account of traffic diversion on main internal roads because of non completion of ROB by PWD(B&R). EE asked to personally follow up the case for Forest clearance with DFO (Sangrur). |
Observation Raised by SE : | |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | Kind attn SE Pta
Kindly get the permissions from other departments with out further delays |
Observation Raised by EIC : | Need urgent intervention from Local Level |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | Yes |