Scope of Work Component Wise |
|
23.98 |
|
|
1 |
|
|
|
1 |
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
26.7 KM |
KM |
% |
100 % |
|
|
|
100 % |
% |
% |
Financial Progress : | 1108.77 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2019-07-31 18:13:52 |
Comment by JE in last visit : | Reinforcement binding & Shuttering Work for C- Tech basin for STP in Zone 2 SANGRUR is in Progress |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2019-02-08 12:42:40 |
Comment by SDO : | MPS Khanauri |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2019-07-22 09:19:38 |
Comment by XEN on last visit : | NRCP works at Moonak, Lehragaga and Khanauri towns completed |
Observation Raised by XEN : | |
Date of Visit by SE : | |
Comment by SE on last visit : | |
Observation Raised by SE : | |
Date of Visit by CE : | 2018-05-10 16:17:23 |
Comment by CE on last visit : | Mps& stp inspection 4mld lehragaga |
Observation Raised by CE : | |
Comment by EIC : | Kindly start uploading the results of the STP |
Observation Raised by EIC : | Need urgent intervention from Local Level |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |