Scope of Work Component Wise |
|
|
22.84 |
|
|
|
|
|
|
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
KM |
12.39 KM |
% |
% |
|
|
2600 |
% |
% |
% |
Financial Progress : | 1135 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-08-27 15:46:39 |
Comment by JE in last visit : | Construction of 1000mm I'd manhole near verka chownk |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | |
Comment by SDO : | |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-08-03 13:46:45 |
Comment by XEN on last visit : | Excavation of 1000 mm diameter sewer at Batala road. Approx 60 mtr gap was left by Jyoti buildtech. Out of which 30 mtr has been laid. Work stopped today by factory owner has now been resumed with intervention of area councilor. Pipe laying likely to be completed tomorrow. |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-09-12 10:45:21 |
Comment by SE on last visit : | MH at 1000 mm constructed. Laying of slab is pending which will be laid tomorrow. |
Observation Raised by SE : | |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | It may ensured that work be done accordingly PWSSB specification strictly. |
Observation Raised by EIC : | Need Intervention from Local Level |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |