Scope of Work Component Wise |
|
4.21 |
43.56 |
|
|
|
|
|
|
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
5.21 KM |
47.67 KM |
% |
% |
|
|
5662 |
% |
% |
% |
Financial Progress : | 1498 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-07-24 17:03:42 |
Comment by JE in last visit : | Brick compressive strength test |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2018-07-18 12:32:33 |
Comment by SDO : | Dismentaling oc cc work in progress at ram nagar verkafor laying sewer |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-04-18 16:36:30 |
Comment by XEN on last visit : | Manhole construction on progress at dhupsari, verka |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-07-18 12:25:30 |
Comment by SE on last visit : | Work completed except laying of 200 m SWP Sewer and 50 house connections on this line. Cc being dismentalled to lay sewer. |
Observation Raised by SE : | |
Date of Visit by CE : | 2018-03-21 15:46:48 |
Comment by CE on last visit : | 200 mm diameter sewer at dhupsari, Verka. Smoke test conducted and three joints leaked. Same are to be repaired. |
Observation Raised by CE : | |
Comment by EIC : | good report |
Observation Raised by EIC : | |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |