Scope of Work Component Wise |
|
|
|
3 |
|
|
|
|
|
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
KM |
KM |
93 % |
% |
|
|
|
% |
% |
% |
Financial Progress : | 75 Lacs |
Physical Progress : | 93 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-07-09 12:30:01 |
Comment by JE in last visit : | Tubewell commissioned |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2018-07-09 12:33:44 |
Comment by SDO : | Ram bagh tubewell recently cimmisiond |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-06-08 10:23:54 |
Comment by XEN on last visit : | All tubewells commissioned, chlorine tested at Badala road tubewell, found in between 0.5-0.6 ppm. |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-06-08 10:23:28 |
Comment by SE on last visit : | Tube well commissioned. Residual chlorine checked and found to be 0.5ppm at source. |
Observation Raised by SE : | |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | Kindly upload the discharge received details |
Observation Raised by EIC : | Need urgent intervention from Local Level |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |