Column Filters
Weekly Reports
Name of Work | Provindg laying water supply (Under PMIDC)(Lehragaga) |
Agency Name | Sh. Tarsem Chand Garg |
Project Cost | Rs 54 Lacs |
Start Date | 06-03-2013 |
End Date | 05-09-2013 |
Revised Date | 05-09-2013 |
Je Incharge | Sh. Tejinder Kumar |
SDE Incharge | Sh. Gurpreet Singh Sekhon |
Engineer Incharge | Sh. Amandeep Singh |
Components | Program water supply | Main sewer | Lateral sewer | Tubewell | Stp | Water supply | Water supply conn | Sewer conn | Mps | Ohsr | Wtp |
---|---|---|---|---|---|---|---|---|---|---|---|
Scope of Work Component Wise | 6.22 | ||||||||||
Progress during this week (Week 4) | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Progress Till Date | 6.22 KM | KM | KM | % | % | % | % | % | |||
Financial Progress : | Lacs | ||||||||||
Physical Progress : | 100 % | ||||||||||
Is any observation pending by 3rd Party : | |||||||||||
Date of Visit by Je: | 2018-02-07 16:53:41 | ||||||||||
Comment by JE in last visit : | MPS Lehragaga | ||||||||||
Observation Raised by JE : | All is well | ||||||||||
Date of Visit by SDO : | |||||||||||
Comment by SDO : | |||||||||||
Observation Raised by SDO : | |||||||||||
Date of Visit by XEN : | |||||||||||
Comment by XEN on last visit : | |||||||||||
Observation Raised by XEN : | |||||||||||
Date of Visit by SE : | |||||||||||
Comment by SE on last visit : | |||||||||||
Observation Raised by SE : | |||||||||||
Date of Visit by CE : | |||||||||||
Comment by CE on last visit : | |||||||||||
Observation Raised by CE : | |||||||||||
Comment by EIC : | |||||||||||
Observation Raised by EIC : | |||||||||||
Pending material Inspection Reports : | No | ||||||||||
Any Drawings pending for approval with xen: | No | ||||||||||
Any 3rd Party Inspection Report Pending for compliance : | No |