Scope of Work Component Wise |
|
|
|
4 |
|
|
|
|
|
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
KM |
KM |
99 % |
% |
|
|
|
% |
% |
% |
Financial Progress : | 109 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-05-18 09:08:17 |
Comment by JE in last visit : | Tubewell commissioned |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2018-05-14 16:31:49 |
Comment by SDO : | Commissioned tubewell |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-04-27 16:46:19 |
Comment by XEN on last visit : | Work completed, tubewells handed over to MC after commissioning. |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-03-23 10:46:00 |
Comment by SE on last visit : | - |
Observation Raised by SE : | |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | Kindly upload close viewed photos only |
Observation Raised by EIC : | Need Intervention from Local Level |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |