Progress Report

Column Filters

Weekly Reports

Name of WorkProviding Water Supply, Sewerage, OHSR, IPS(Kharar)
Agency NameSh. Joginder Singh Contractor, Mohali
Project CostRs 657 Lacs
Start Date 04-11-2016
End Date31-01-2018
Revised Date31-01-2018
Je InchargeSh. Rajnish Painuli
SDE InchargeSh. Tarun Gupta
Engineer InchargeSh. Rahul Kaushal
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 13.41 6.58 1598 3256 1 (Repair)
Progress during this week (Week 4) 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date 5.20 KM KM 8.53 KM % % 472 475 1055 % 99 % %
Financial Progress :299 Lacs
Physical Progress :75 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-10-31 16:14:54
Comment by JE in last visit :work in progress
Observation Raised by JE :Red Flag
Date of Visit by SDO :2018-10-31 16:14:50
Comment by SDO :Work of pipes completed
Observation Raised by SDO :
Date of Visit by XEN :2019-03-11 11:57:44
Comment by XEN on last visit :Work completed except court case related work. All sewer & water supply lines commissioned.
Observation Raised by XEN :
Date of Visit by SE :2019-03-11 12:10:11
Comment by SE on last visit :Work completed including w/S, sewerage, repair of OHSR etc. except the work of IPS and 2km sewer & 800m rising main which EE explained that it could not be taken up because of court orders. EE asked to take up the matter at personal level in Distt courts for getting clearance for execution of balance works.
Observation Raised by SE :
Date of Visit by CE :2018-07-12 11:03:38
Comment by CE on last visit :IPS site visited which is under dispute and court has stayed the work. XEN & SDE advised to peruse to case with help of MC authorities to vacate the stay so that IPS work may be taken in hand and sewerage around Badala road can be commissioned.
Observation Raised by CE :
Comment by EIC :ensure commissioning of the OHSR as early as possible so that it cabe put in use in summer season
Observation Raised by EIC :Need urgent intervention from Local Level
Pending material Inspection Reports :Yes (1)-2018-10-10 12:44:22
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No