Scope of Work Component Wise |
|
3.45 |
20.07 |
|
|
|
|
|
|
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
3.20 KM |
17.77 KM |
% |
% |
|
|
1280 |
% |
% |
% |
Financial Progress : | 1223 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-08-27 17:09:12 |
Comment by JE in last visit : | Check House connection work going on 600mmx450mm |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2018-08-04 11:31:03 |
Comment by SDO : | Handing process is going on for MC staff at bye pass at ganupur kala |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-07-06 17:20:48 |
Comment by XEN on last visit : | House connections chamber work in progress |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-07-18 11:25:21 |
Comment by SE on last visit : | Progress not up to the mark. As informed by EE/SDE, appox 400 m length of SW Sewer for making connection and 19 MH still pending. Advised to complete the work by end of this month. EE to give personal attention please. |
Observation Raised by SE : | Need urgent intervention from Local Level |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | I think whole the front is clear now. stick to the target date for completion |
Observation Raised by EIC : | Need urgent intervention from Local Level |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |