Progress Report

Column Filters

Weekly Reports

Name of WorkProviding laying Water Supply(Sunam)
Agency NameSh. Jai Bhushan Malik
Project CostRs 417 Lacs
Start Date 05-08-2016
End Date04-02-2017
Revised Date04-02-2017
Je InchargeSh. Simranjeet Singh
SDE InchargeSh. Gurpreet Singh Sekhon
Engineer InchargeSh. Amandeep Singh
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 26.03 3000
Progress during this week (Week 4) 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date 24.80 KM KM KM % % 1610 1610 % % %
Financial Progress :344.80 Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-02-07 16:17:50
Comment by JE in last visit :Work completed
Observation Raised by JE :All is well
Date of Visit by SDO :
Comment by SDO :
Observation Raised by SDO :
Date of Visit by XEN :
Comment by XEN on last visit :
Observation Raised by XEN :
Date of Visit by SE :
Comment by SE on last visit :
Observation Raised by SE :
Date of Visit by CE :
Comment by CE on last visit :
Observation Raised by CE :
Comment by EIC :
Observation Raised by EIC :
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No