Scope of Work Component Wise |
|
|
19.94 |
|
|
|
|
|
|
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
KM |
18.90 KM |
% |
% |
|
|
|
% |
% |
% |
Financial Progress : | 372 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-12-11 13:13:32 |
Comment by JE in last visit : | Work in progress |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2018-11-16 10:21:40 |
Comment by SDO : | |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-10-12 13:39:08 |
Comment by XEN on last visit : | Work progress slow due to shops present on both sides, railway boundary in alignment.
Agency instructed to expedite progress by taking proper safety measures.
Case for laying sewer in railway boundary to be done by thrusting. |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-03-21 11:08:10 |
Comment by SE on last visit : | Progress of Work very slow as time limit is already over |
Observation Raised by SE : | Need urgent intervention from Local Level |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | No visit above SDE is on record. work is going on since 4/15 and till date progress is 92%. The photos uploaded are of no technical use.The back filling of earth seems without compacting and watering |
Observation Raised by EIC : | Need urgent intervention from Local Level |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |