Progress Report

Column Filters

Weekly Reports

Name of Workproviding laying sewerage work (Sub Contract No. JICA-004-03)(Amritsar(MC))
Agency NameM/s. Oriental Ceramics Refractories
Project CostRs 1169 Lacs
Start Date 14-12-2016
End Date31-01-2018
Revised Date15-08-2018
Je InchargeSh. Jagdeep Singh
SDE InchargeSh. Harpreet Singh
Engineer InchargeSh. S.K.Ranga
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 3.46 25.96
Progress during this week (Week 4) 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM 4.78 KM 10.35 KM % % 1280 % % %
Financial Progress :1164 Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-10-08 16:20:54
Comment by JE in last visit :Rider sewer for house connections in gumtala vill.
Observation Raised by JE :All is well
Date of Visit by SDO :2018-07-19 17:01:37
Comment by SDO :Plaster work of manhole is in progress at jujhar Singh Ave at gumtala link road
Observation Raised by SDO :
Date of Visit by XEN :2018-07-14 16:13:25
Comment by XEN on last visit :Sample of coarse sand taken from site at merankot road. It was tested in contractor's lab. FM came out to be 3.2. which is OK
Observation Raised by XEN :
Date of Visit by SE :2018-09-12 10:25:51
Comment by SE on last visit :WH Construction in progress in gali no. 11, Jhujar Avenue.
Observation Raised by SE :
Date of Visit by CE :2018-03-21 14:55:00
Comment by CE on last visit :Encroachment site excavation work in progress. Already 130 mtr sewer laid
Observation Raised by CE :
Comment by EIC :Target date is over , the work is still going on. Be carefull
Observation Raised by EIC :Need urgent intervention from Local Level
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No