Scope of Work Component Wise |
|
|
|
|
|
4.1 |
|
|
|
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
KM |
3.44 KM |
% |
% |
|
|
|
% |
% |
% |
Financial Progress : | 67 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-05-17 11:03:26 |
Comment by JE in last visit : | Work in progress |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2018-05-17 11:05:51 |
Comment by SDO : | Sewer line laid. MH constructed. Connection with existing sewer line in progess. |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-05-04 15:03:39 |
Comment by XEN on last visit : | Manhole slabs casted for laid sewer. |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-03-21 12:19:03 |
Comment by SE on last visit : | About 800m balance due to pending permission from GAIL. EE asked to pursue at personal level without any further delay. |
Observation Raised by SE : | Need urgent intervention from Local Level |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | |
Observation Raised by EIC : | |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |