Progress Report

Column Filters

Weekly Reports

Name of WorkBoring & intallation of Tubewell (Nangal)
Agency NameM/s Guru Nanak Tubewell Company, Ambala
Project CostRs 27 Lacs
Start Date 20-06-2017
End Date31-03-2018
Revised Date30-06-2019
Je InchargeSh. Lovekesh Kumar
SDE InchargeSh. Tarun Gupta
Engineer InchargeSh. Rahul Kaushal
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 1
Progress during this week (Week 4) 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM KM KM 100 % % % % %
Financial Progress :25 Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2019-04-04 09:16:09
Comment by JE in last visit :Work in progress
Observation Raised by JE :All is well
Date of Visit by SDO :2018-11-16 10:08:20
Comment by SDO :Work in progress
Observation Raised by SDO :
Date of Visit by XEN :2018-10-12 14:33:48
Comment by XEN on last visit :Tubewell commissioned & chlorinator installed, pump chamber work balance. Agency instructed to complete balance work at the earliest.
Observation Raised by XEN :
Date of Visit by SE :2018-03-21 12:52:32
Comment by SE on last visit :Work progress is very slow which according to EE is due to rocky strata.
Observation Raised by SE :Need Intervention from Local Level
Date of Visit by CE :
Comment by CE on last visit :
Observation Raised by CE :
Comment by EIC :Kindly commission this tw immediately
Observation Raised by EIC :Need urgent intervention from Local Level
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No