Scope of Work Component Wise |
|
2.38 |
63.74 |
|
|
|
|
8400 |
|
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
0.74 KM |
63.6 KM |
% |
% |
|
|
6155 |
% |
% |
% |
Financial Progress : | 2612 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-04-26 16:52:05 |
Comment by JE in last visit : | Main sewer pending from court chowk to ITI chowk. In principle approval given by regional office Chandigarh.case pending for final approval |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2018-03-22 17:54:10 |
Comment by SDO : | |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2019-12-16 17:24:10 |
Comment by XEN on last visit : | 1100 mm dia main sewer is in progress. Work of STP and branch sewer in village Sangerha is also in progress. Agency is directed to complete the balance work |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-08-09 16:30:42 |
Comment by SE on last visit : | During site visit, the public complained regarding non completion of bituminous roads & main sewer alloted under urban mission. It was learnt that EE Mr SD Kansal had finalised the bill of the agency even without getting major part of main sewer and bituminous roads executed. It was learnt that IL pavers were got laid in 90000 sqm against alloted scope of 30000 sqm while leaving out above said major items. Incumbent EE asked to submit detailed report on the issue so that further action can be taken. EE asked to follow up the pending case for cutting of trees with NGT, Nee Delhi. |
Observation Raised by SE : | |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | No visit by the officer above SDO is on record after 22 March
For Kind attn. of SE Patiala . He should personally pursue the case with Forest department |
Observation Raised by EIC : | |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |