Scope of Work Component Wise |
|
|
|
|
|
10.96 |
|
|
|
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
10.80 KM |
KM |
KM |
% |
% |
|
|
|
% |
% |
% |
Financial Progress : | Lacs |
Physical Progress : | % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-04-11 11:34:59 |
Comment by JE in last visit : | Final bill prepared |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2018-04-12 15:05:12 |
Comment by SDO : | Work completed. Final bill under preperation |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-05-04 16:25:58 |
Comment by XEN on last visit : | Work physically completed but connection with existing tubewells pending due to dispute of WSSD with MC because of pending arrears. |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-03-21 11:36:57 |
Comment by SE on last visit : | EE told that work stands completed. EE asked to check and explain difference between scope & progress. |
Observation Raised by SE : | Need Intervention from Local Level |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | |
Observation Raised by EIC : | |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |