Scope of Work Component Wise |
|
|
|
|
5.5 |
|
|
|
|
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
KM |
KM |
% |
100 % |
|
|
|
% |
% |
% |
Financial Progress : | 544 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2019-05-31 10:54:53 |
Comment by JE in last visit : | Plant commissioned |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2019-07-02 12:40:40 |
Comment by SDO : | STP Morinda in working order |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2019-08-27 15:20:59 |
Comment by XEN on last visit : | STP in operation. |
Observation Raised by XEN : | |
Date of Visit by SE : | 2019-09-27 11:16:44 |
Comment by SE on last visit : | STP under stabilisation. Test results for sample taken by PPCB on 8/8/19 are awaited. No proper flow at outlet.. Decanters not working properly. Agency/EE to look into & sort out the issue reg RCC main. |
Observation Raised by SE : | |
Date of Visit by CE : | 2018-07-12 13:12:22 |
Comment by CE on last visit : | Civil work completed except boundary wall, road work & staff quarter. Mechanical fitting work in progress.
Agency ensured that STP will be made operational by 15.09.2018. |
Observation Raised by CE : | |
Comment by EIC : | 1 No visit by the officer above SDE is on record after 21st March
2. Kindly upload photos of close view of the work
For Kind attn. of SE |
Observation Raised by EIC : | |
Pending material Inspection Reports : | Yes (9)-2018-04-30 01:46:22 |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |