Progress Report

Column Filters

Weekly Reports

Name of WorkProviding Sewerage works (Morinda)
Agency NameSh. Parveet Singh Contractor, Mohali
Project CostRs 229 Lacs
Start Date 22-08-2016
End Date31-12-2017
Revised Date28-02-2019
Je InchargeSh. Rajnish Painuli
SDE InchargeSh. Tarun Gupta
Engineer InchargeSh. Rahul Kaushal
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 0.37 4.6 1223
Progress during this week (Week 4) 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM 0.38 KM 3.61 KM % % 540 % % %
Financial Progress :221.51 Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-12-20 14:39:59
Comment by JE in last visit :work in progress
Observation Raised by JE :All is well
Date of Visit by SDO :2019-01-30 16:52:41
Comment by SDO :Paver block road
Observation Raised by SDO :
Date of Visit by XEN :2019-03-11 12:19:27
Comment by XEN on last visit :Work completed.
Observation Raised by XEN :
Date of Visit by SE :2018-04-25 09:46:42
Comment by SE on last visit :EE to coordinate with MC for earth filling in low lying areas & get balance sewer lines laid. EE asked to upload scope & progress of roadworks roadworks also & ensure its early completion.
Observation Raised by SE :
Date of Visit by CE :2018-04-18 11:46:31
Comment by CE on last visit :Sewer work 95%complete and reconditioning with dismantled tiles in progress
Observation Raised by CE :
Comment by EIC :
Observation Raised by EIC :
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No