Progress Report

Column Filters

Weekly Reports

Name of Workprovinding laying sewerage work & const. of MPS (Kiratpur Sahib)
Agency NameSh. Parveet Singh Contractor, Mohali
Project CostRs 263 Lacs
Start Date 23-12-2016
End Date30-06-2018
Revised Date30-09-2020
Je InchargeSh. Lovekesh Kumar
SDE InchargeSh. Tarun Gupta
Engineer InchargeSh. Rahul Kaushal
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 0.21 3.12 809 6 mld
Progress during this week (Week 4) 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM 0.1 KM 2.6 KM % % 66 99 % % %
Financial Progress :255 Lacs
Physical Progress :99 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2019-07-24 09:02:44
Comment by JE in last visit :Work in progress
Observation Raised by JE :Red Flag
Date of Visit by SDO :2019-07-19 11:20:40
Comment by SDO :Progress of work severely affected by rain
Observation Raised by SDO :
Date of Visit by XEN :2019-12-04 15:07:16
Comment by XEN on last visit :Sewer work in progress.
Observation Raised by XEN :
Date of Visit by SE :2018-03-21 13:24:15
Comment by SE on last visit :Work is standstill. EE to take action
Observation Raised by SE :Need urgent intervention from Local Level
Date of Visit by CE :
Comment by CE on last visit :
Observation Raised by CE :
Comment by EIC :Photos uploaded are of no use as are not easy to understand the actual situation at site. Kindly upload the close viewed photographs only to see the quality of work
Observation Raised by EIC :Need urgent intervention from Local Level
Pending material Inspection Reports :Yes (1)-2018-05-08 22:06:21
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No