Scope of Work Component Wise |
|
0.21 |
3.12 |
|
|
|
|
809 |
6 mld |
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
0.1 KM |
2.6 KM |
% |
% |
|
|
66 |
99 % |
% |
% |
Financial Progress : | 255 Lacs |
Physical Progress : | 99 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2019-07-24 09:02:44 |
Comment by JE in last visit : | Work in progress |
Observation Raised by JE : | Red Flag |
Date of Visit by SDO : | 2019-07-19 11:20:40 |
Comment by SDO : | Progress of work severely affected by rain |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2019-12-04 15:07:16 |
Comment by XEN on last visit : | Sewer work in progress. |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-03-21 13:24:15 |
Comment by SE on last visit : | Work is standstill. EE to take action |
Observation Raised by SE : | Need urgent intervention from Local Level |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | Photos uploaded are of no use as are not easy to understand the actual situation at site. Kindly upload the close viewed photographs only to see the quality of work |
Observation Raised by EIC : | Need urgent intervention from Local Level |
Pending material Inspection Reports : | Yes (1)-2018-05-08 22:06:21 |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |