Progress Report

Column Filters

Weekly Reports

Name of Workproviding laying sewerage work (Sub Contract No. JICA-004-01)(Amritsar(MC))
Agency NameM/s. Oriental Ceramics Refractories
Project CostRs 1546 Lacs
Start Date 14-12-2016
End Date31-01-2018
Revised Date31-01-2018
Je InchargeSh. Kulbir Singh
SDE InchargeSh. Harpreet Singh
Engineer InchargeSh. S.K.Ranga
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 2.66
Progress during this week (Week 4) 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM 2.53 KM KM % % % % %
Financial Progress :1496 Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-04-13 13:00:54
Comment by JE in last visit :Curing of slab of 2600mm dia sewer manhole
Observation Raised by JE :All is well
Date of Visit by SDO :2018-04-13 13:06:38
Comment by SDO :Curing of slabof 2600 mm dia sewer near Radha swami bhawan
Observation Raised by SDO :
Date of Visit by XEN :2018-05-09 09:20:54
Comment by XEN on last visit :Sewer work completed. Road work in progress by PWD (B&R)
Observation Raised by XEN :
Date of Visit by SE :2018-05-09 09:21:54
Comment by SE on last visit :
Observation Raised by SE :
Date of Visit by CE :2018-04-13 15:18:07
Comment by CE on last visit :Last Manhole near STP. Plaster in progress
Observation Raised by CE :
Comment by EIC :It may be ensured that work is completed with in stipulated period
Observation Raised by EIC :Need Intervention from Local Level
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No