Scope of Work Component Wise |
|
2.66 |
|
|
|
|
|
|
|
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
2.53 KM |
KM |
% |
% |
|
|
|
% |
% |
% |
Financial Progress : | 1496 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-04-13 13:00:54 |
Comment by JE in last visit : | Curing of slab of 2600mm dia sewer manhole |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2018-04-13 13:06:38 |
Comment by SDO : | Curing of slabof 2600 mm dia sewer near Radha swami bhawan |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-05-09 09:20:54 |
Comment by XEN on last visit : | Sewer work completed. Road work in progress by PWD (B&R) |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-05-09 09:21:54 |
Comment by SE on last visit : | |
Observation Raised by SE : | |
Date of Visit by CE : | 2018-04-13 15:18:07 |
Comment by CE on last visit : | Last Manhole near STP. Plaster in progress |
Observation Raised by CE : | |
Comment by EIC : | It may be ensured that work is completed with in stipulated period |
Observation Raised by EIC : | Need Intervention from Local Level |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |