Name of Work | Provinding laying water supply & Sewerage Network(Gidderbaha) |
Agency Name | M/s Saini Const. Co. |
Project Cost | Rs 653 Lacs |
Start Date | 15-02-2016 |
End Date | 31-07-2017 |
Revised Date | 31-07-2017 |
Je Incharge | Sh. Harjinder Singh |
SDE Incharge | Sh. Ravi Kumar |
Engineer Incharge | Sh. Gurvinder Pal Singh |
Components | Program water supply | Main sewer | Lateral sewer | Tubewell | Stp | Water supply | Water supply conn | Sewer conn | Mps | Ohsr | Wtp |
---|---|---|---|---|---|---|---|---|---|---|---|
Scope of Work Component Wise | 10.08 | 11.7 | 1500 | 1350 | |||||||
Progress during this week (Week 4) | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |