Column Filters
Weekly Reports
Name of Work | Const. of OHSR(Patran) |
Agency Name | Sh. Shyam Kumar & Sudershan Kumar |
Project Cost | Rs 58 Lacs |
Start Date | 12-07-2016 |
End Date | 06-09-2017 |
Revised Date | 06-09-2017 |
Je Incharge | Sh. Pardeep Singh |
SDE Incharge | Sh. Rajeev Kapoor |
Engineer Incharge | Sh. Sabjit Singh |
Components | Program water supply | Main sewer | Lateral sewer | Tubewell | Stp | Water supply | Water supply conn | Sewer conn | Mps | Ohsr | Wtp |
---|---|---|---|---|---|---|---|---|---|---|---|
Scope of Work Component Wise | 1 (1 Lac Gallan) | ||||||||||
Progress during this week (Week 4) | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Progress Till Date | 0 KM | 0 KM | 0 KM | 0 % | 0 % | 0 | 0 % | 100 % | 0 % | ||
Financial Progress : | Lacs | ||||||||||
Physical Progress : | % | ||||||||||
Is any observation pending by 3rd Party : | |||||||||||
Date of Visit by Je: | 2018-04-17 09:34:43 | ||||||||||
Comment by JE in last visit : | All is well | ||||||||||
Observation Raised by JE : | All is well | ||||||||||
Date of Visit by SDO : | 2018-03-21 10:55:05 | ||||||||||
Comment by SDO : | Work completed | ||||||||||
Observation Raised by SDO : | |||||||||||
Date of Visit by XEN : | |||||||||||
Comment by XEN on last visit : | |||||||||||
Observation Raised by XEN : | |||||||||||
Date of Visit by SE : | |||||||||||
Comment by SE on last visit : | |||||||||||
Observation Raised by SE : | |||||||||||
Date of Visit by CE : | |||||||||||
Comment by CE on last visit : | |||||||||||
Observation Raised by CE : | |||||||||||
Comment by EIC : | |||||||||||
Observation Raised by EIC : | |||||||||||
Pending material Inspection Reports : | No | ||||||||||
Any Drawings pending for approval with xen: | No | ||||||||||
Any 3rd Party Inspection Report Pending for compliance : | No |