Progress Report

Column Filters

Weekly Reports

Name of WorkProvindg laying Sewerage work const. of MPS(Badhni Kalan)
Agency NameM/s, Varindra Buildcon
Project CostRs 261 Lacs
Start Date 23-12-2016
End Date
Revised Date
Je InchargeSh. Gurpreet Singh
SDE InchargeSh. Maninder Singh
Engineer InchargeSh. Parul Goyal
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 1.29 0.67 1
Progress during this week (Week 4) 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM 0.49 KM 0 KM % % 0 % % %
Financial Progress :61.37 Lacs
Physical Progress :25 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-12-12 12:25:44
Comment by JE in last visit :Work of MPS held up due to non availability of land
Observation Raised by JE :Red Flag
Date of Visit by SDO :2018-05-12 10:47:28
Comment by SDO :There is a quarrel between two parties about MPS land which is already given by BADHANI KALAN NPA and case shifted from local police to SDM court NIHAL SINGH WALA whose date Is 24th MAY 2018
Observation Raised by SDO :
Date of Visit by XEN :2018-07-10 16:37:59
Comment by XEN on last visit :Meeting with sho and president in Badhani kalan for mps site.
Observation Raised by XEN :
Date of Visit by SE :
Comment by SE on last visit :
Observation Raised by SE :
Date of Visit by CE :
Comment by CE on last visit :
Observation Raised by CE :
Comment by EIC :KIND ATTENTION 1. Visit during last 30 days of an officer above SDE is not on record
Observation Raised by EIC :Need urgent intervention from Local Level
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No