Scope of Work Component Wise |
|
155.01 |
|
|
|
|
|
17500 |
|
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
31.94 KM |
114 KM |
% |
% |
|
|
13550 |
% |
% |
% |
Financial Progress : | 6178 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-03-22 10:44:44 |
Comment by JE in last visit : | At site Guru ki wadali laying of 200mm construction of Manhole |
Observation Raised by JE : | Red Flag |
Date of Visit by SDO : | 2018-03-24 15:26:18 |
Comment by SDO : | |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-03-24 15:27:02 |
Comment by XEN on last visit : | Checking thickness of PCC bed of 200 mm diameter line at sun sahib road |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-04-04 16:36:39 |
Comment by SE on last visit : | Work completed on 31st. Br sewer laid appox 113.5 km aganist 121.71 km. RCC Pipe sewer laid 31.94 km aganist 26.98 km. No nishans were now available and hence completion declared.
Now at down stream end in Ranjitpura colony. Handing over to MC is main issue with EE. |
Observation Raised by SE : | Need urgent intervention from Local Level |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | results of checking and testing be also uploaded |
Observation Raised by EIC : | |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |