Scope of Work Component Wise |
|
|
|
|
|
3.255 |
|
|
|
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
3.255 KM |
KM |
KM |
% |
% |
650 |
|
|
% |
% |
% |
Financial Progress : | 41.40 Lacs |
Physical Progress : | 100 % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2018-08-11 11:28:54 |
Comment by JE in last visit : | Interlocking tiles |
Observation Raised by JE : | Need Intervention from Local Level |
Date of Visit by SDO : | 2018-07-30 13:04:48 |
Comment by SDO : | work in progress sarpanch colony |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2018-07-19 12:43:14 |
Comment by XEN on last visit : | JE and SDE are advised to get CC 1:8:16 tested from outside lab immediately |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-06-22 09:53:59 |
Comment by SE on last visit : | Visit of STP SITE at kartarpur |
Observation Raised by SE : | |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | Kindly ensure where IL tile work is to be done that 1. Use tile cutters to properly fit in the part of tile 2. Fix edge row of tiles with mortar 3. Cast rectangular comings of such manhole cover |
Observation Raised by EIC : | Need urgent intervention from Local Level |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |