Progress Report

Column Filters

Weekly Reports

Name of Workprovinding laying sewerage work (under NRCP )(Jalandhar (MC))
Agency NameM/s Ludhiana Const. Co., Ludhiana
Project CostRs 432 Lacs
Start Date 01-08-2016
End Date31-12-2017
Revised Date31-12-2017
Je InchargeSh. Deepak Kumar Khurana
SDE InchargeSh. Balraj Singh
Engineer InchargeSh. Jitin Vasudeva
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 1.768 27.182
Progress during this week (Week 4) 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM 1.768 KM 27.182 KM % % % % %
Financial Progress : Lacs
Physical Progress :100 %
Is any observation pending by 3rd Party :
Date of Visit by Je:2018-08-31 17:54:30
Comment by JE in last visit :Railway crossing is being done by railway department
Observation Raised by JE :All is well
Date of Visit by SDO :2018-08-25 13:17:38
Comment by SDO :Thrusting of R.C.C.pipe work of railway crossing jalandhar to ferozpur is in progress
Observation Raised by SDO :
Date of Visit by XEN :2018-08-25 17:08:04
Comment by XEN on last visit :Railway crossing of RCC NP4 pipe is under progress under Jalandhar- Ferozepur Railway line. Thrusting of RCC Blocks has been completed. Laying of RCC pipes is being done. 4 No. Pipes have been laid out of 16 No.s. SDE is directed to monitor the work regularly and report on daily basis regarding progress of work and also to ensure that the work is being carried out as per design and drawings by railway authority.
Observation Raised by XEN :
Date of Visit by SE :2018-07-01 18:54:17
Comment by SE on last visit :
Observation Raised by SE :
Date of Visit by CE :
Comment by CE on last visit :
Observation Raised by CE :
Comment by EIC :
Observation Raised by EIC :Need urgent intervention from Local Level
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No