Name of WorkProviding laying water supply (Ajnala)
Agency NameM/S Natha Singh Contractors
Project CostRs 341 Lacs
Start Date 19-09-2016
End Date18-01-2017
Revised Date18-01-2017
Je InchargeSh. Gurbhej Singh
SDE InchargeSh. Harpreet Singh
Engineer InchargeSh Pankaj Jain
Components Program water supply Main sewer Lateral sewer Tubewell Stp Water supply Water supply conn Sewer conn Mps Ohsr Wtp
Scope of Work Component Wise 9.05 1325
Progress during this week (Week 4) 0 0 0 0 0 0 0 0 0 0 0
Progress Till Date KM KM KM % % 9.00 280 % % %
Financial Progress : Lacs
Physical Progress : %
Is any observation pending by 3rd Party :
Date of Visit by Je:2019-07-05 11:31:34
Comment by JE in last visit :Interlocking tiles work started
Observation Raised by JE :All is well
Date of Visit by SDO :2019-07-05 11:37:23
Comment by SDO :Water supply lines completed and interlocking tile work is in progress
Observation Raised by SDO :
Date of Visit by XEN :2019-07-05 13:53:57
Comment by XEN on last visit :Water supply distribution lines work completed. Balance work of road work has been restarted as per direction of MLA Ajnala
Observation Raised by XEN :
Date of Visit by SE :2018-03-21 16:39:09
Comment by SE on last visit :As told by contractor, he has laid appox 9 km and not 6.47 as recommended by field stall. Work held up since one year as no funds under Urban Mission were released. At two places water pipes laid has not been connected. All we're directed to make these co
Observation Raised by SE :Need urgent intervention from Local Level
Date of Visit by CE :
Comment by CE on last visit :
Observation Raised by CE :
Comment by EIC :Kind Attn XEN Now th problem of funds is over. Send requirement as per passed bills lying with you. The funds will be released within a day ort two. ask the contractor to start immediately or proceed as per CA
Observation Raised by EIC :Need urgent intervention from Local Level
Pending material Inspection Reports :No
Any Drawings pending for approval with xen:No
Any 3rd Party Inspection Report Pending for compliance :No