Scope of Work Component Wise |
|
|
|
|
|
9.05 |
1325 |
|
|
|
|
Progress during this week (Week 4) |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Progress Till Date |
KM |
KM |
KM |
% |
% |
9.00 |
280 |
|
% |
% |
% |
Financial Progress : | Lacs |
Physical Progress : | % |
Is any observation pending by 3rd Party : | |
Date of Visit by Je: | 2019-07-05 11:31:34 |
Comment by JE in last visit : | Interlocking tiles work started |
Observation Raised by JE : | All is well |
Date of Visit by SDO : | 2019-07-05 11:37:23 |
Comment by SDO : | Water supply lines completed and interlocking tile work is in progress |
Observation Raised by SDO : | |
Date of Visit by XEN : | 2019-07-05 13:53:57 |
Comment by XEN on last visit : | Water supply distribution lines work completed. Balance work of road work has been restarted as per direction of MLA Ajnala |
Observation Raised by XEN : | |
Date of Visit by SE : | 2018-03-21 16:39:09 |
Comment by SE on last visit : | As told by contractor, he has laid appox 9 km and not 6.47 as recommended by field stall. Work held up since one year as no funds under Urban Mission were released. At two places water pipes laid has not been connected. All we're directed to make these co |
Observation Raised by SE : | Need urgent intervention from Local Level |
Date of Visit by CE : | |
Comment by CE on last visit : | |
Observation Raised by CE : | |
Comment by EIC : | Kind Attn XEN
Now th problem of funds is over. Send requirement as per passed bills lying with you. The funds will be released within a day ort two. ask the contractor to start immediately or proceed as per CA |
Observation Raised by EIC : | Need urgent intervention from Local Level |
Pending material Inspection Reports : | No |
Any Drawings pending for approval with xen: | No |
Any 3rd Party Inspection Report Pending for compliance : | No |