Column Filters
Check list for inspection of Material
Dated : 2018-06-19 01:55:08
Name of Work | Cluster of Sangrur & Dhuri |
Agency Name | M/s. Shapoorji Pallonji Co. Ltd |
Start Date | 17-06-2016 |
Completion Date | 16-12-2017 |
Cost | Rs 14062 Lac |
JE Incharge | Sh. Ashok verma |
SDE Incharge | Sh. Bhavesh Bansal |
Engineer Incharge | Sh. Amandeep Singh |
Sr.No | Description of Material | As per approved scope of agreement | Already Inspected | Already received at site | In Transit | Balance as per approved scope of agreement | Now offered for Inspection | Make | Balance | Remarks | |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | 800mm i/d RCC S/S pipe having inside HDPE lining as per ISI code IS :458-2003 | 5080 mtr. | 4000 mtr. | 3700 mtr. | Nil | 1250 mtr | 1250 mtr. | N/A | for starting Patiala Road work |