Column Filters
Check list for inspection of Material
Dated : 2018-06-15 04:53:16
Name of Work | Providing Water Supply, Sewerage & MPS |
Agency Name | M/S Rajan Builders |
Start Date | 03-02-2016 |
Completion Date | 28-02-2018 |
Cost | Rs 555 Lac |
JE Incharge | Sh. Gurpreet Singh |
SDE Incharge | Sh. Hari Krishan Sharma |
Engineer Incharge | Ms Lata Chauhan |
Sr.No | Description of Material | As per approved scope of agreement | Already Inspected | Already received at site | In Transit | Balance as per approved scope of agreement | Now offered for Inspection | Make | Balance | Remarks | |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Sluice gate | 3 | 0 | 0 | 0 | 3 | 3 | Bharat industrial Corp | 0 | please do sluice gate inspection | |
2 | vent shaft | 11 | 0 | 0 | 0 | 11 | 11 | Balaji pipe jaipur | 0 | please do vent shaft inspection |