Inspection Report

Column Filters

Check list for inspection of Material

Dated : 2019-06-19 22:55:51

Name of WorkCluster of Faridkot, Jaitu & Kotkapura
Agency NameM/s. Shapoorji Pallonji Co. Ltd
Start Date16-06-2016
Completion Date15-12-2017
CostRs 8695 Lac
JE InchargeSh. Bhola Singh
SDE InchargeSh. Gurpal Singh
Engineer InchargeSh. Parul Goyal
Sr.No Description of Material As per approved scope of agreement Already Inspected Already received at site In Transit Balance as per approved scope of agreement Now offered for Inspection Make Balance Remarks
1 Inspection Call of 315 KVA Transformer for 8 MLD STP at Kotkapura & 250 KVA Transformer for 6 MLD STP at Kotkapura. 2 Nil Nil Nil Nil 2 M/s. Kirloskar Electric Co.Ltd. Nil You are requested to kindly depute TPI M/S. PDIL/CEIL. for inspection please.